| Task
| Date
| Hours Worked
| Percent Complete
|
| create web site template | 25-Jun | 3 | 100%
|
| links for PMO sites | 27-Jun | 4 | 100%
|
| links for Project Charter | 29-Jun | 2 | 10%
|
| links for Product Description | 30-Jun | 2 | 100%
|
| links for Scope Statement | 2-Jul | 1 | 100%
|
| links for Work Breakdown Structure | 2-Jul | 1 | 100%
|
| More links for Project Charter | 2-Jul | 2 | 100%
|
| links for Organization Chart | 3-Jul | 1 | 100%
|
| links for Scope Management Plan | 3-Jul | 1 | 100%
|
| links for Communications Management Plan | 3-Jul | 1 | 100%
|
| links for Project Plan | 3-Jul | 1 | 100%
|
| 1-1 Guidelines | 3-Jul | 2 | 10%
|
| 2-1 Product Description | 3-Jul | 1 | 50%
|
| 2-1 Product Description | 4-Jul | 1 | 80%
|
| 2-2 Project Charter | 3-Jul | 3 | 80%
|
| 2-2 Project Charter | 4-Jul | 1 | 100%
|
| 4-1 Organization Chart | 3-Jul | 1 | 100%
|
| 2-3 Scope Statement | 3-Jul | 3 | 80%
|
| 2-3 Scope Statement | 4-Jul | 1 | 100%
|
| 3-1 Communications Management Plan | 4-Jul | 2 | 100%
|
| 3-2 Project Report | 4-Jul | 2 | 100%
|
| links for Lessons Learned | 4-Jul | 1 | 100%
|
| links for Change Request | 4-Jul | 1 | 100%
|
| links for Project Archives | 4-Jul | 1 | 100%
|
| 3-3 Org Policy on Project Archives | 4-Jul | 2 | 100%
|
| administration of docs, archives and web site | 5-Jul | 2 | 100%
|
| 2-5 Work Breakdown Structure | 5-Jul | 3 | 50%
|
| reformat docs based upon WBS numbering | 5-Jul | 4 | 100%
|
| 3-4 Change Request Form | 5-Jul | 0.5 | 100%
|
| 3-4 Change Request Log | 5-Jul | 0.5 | 100%
|
| 3-4 Change Request Submission for 5 Jul | 5-Jul | 0.5 | 100%
|
| 3-5 Lessons Learned | 5-Jul | 0.5 | 100%
|
| attempts to get PageMaker, InDesign or Quark to work | 6-Jul | 3 | 100%
|
| change global template again (5:30pm - 12:30am) | 6-Jul | 7 | 100%
|
| 5-1 Activity List | 7-Jul | 4 | 100%
|
| begin conversion to Adobe InDesign | 10-Jul | 8 | 10%
|
| drive to stores searching for Adobe CS Standard | 11-Jul | 1 | 100%
|
| document conversion to InDesign | 11-Jul | 9 | 80%
|
| document conversion to InDesign | 11-Jul | 3 | 90%
|
| system admin + install full version of InDesign | 17-Jul | 6 | 100%
|
| 5-2 Activity Sequencing | 18-Jul | 1.5 | 10%
|
| 2-5 Work Breakdown Structure | 23-Jul | 4 | 40%
|
| 2-5 Work Breakdown Structure | 24-Jul | 3 | 50%
|
| 5-2 Network Diagram | 24-Jul | 2 | 100%
|
| 2-6 Formal Acceptance | 24-Jul | 2 | 100%
|
| 4-2-1 RAM | 24-Jul | 2 | 30%
|