The S-Curve derived from project data

| S-Curve
| Time
| Initiation
| Planning
| Executing
| Monitoring
| Closing
| %Complete
| TOTAL
| | 1 | 1 | | | | | 0 | | 1
| | 2 | 2 | | | | | 0 | | 3
| | 3 | 4 | 1 | | | | 1 | | 8
| | 4 | 5 | 3 | | | | 2 | | 16
| | 5 | 4 | 7 | | | | 3 | | 27
| | 6 | 2 | 14 | 1 | | | 5 | | 44
| | 7 | 1 | 16 | 2 | 1 | | 7 | | 64
| | 8 | | 16 | 5 | 1 | | 10 | | 86
| | 9 | | 15 | 8 | 2 | | 13 | | 111
| | 10 | | 14 | 12 | 3 | | 16 | | 140
| | 11 | | 13 | 17 | 4 | | 20 | | 174
| | 12 | | 10 | 24 | 6 | | 24 | | 214
| | 13 | | 8 | 29 | 7 | | 29 | | 258
| | 14 | | 6 | 33 | 8 | | 35 | | 305
| | 15 | | 4 | 37 | 9 | | 41 | | 355
| | 16 | | 4 | 40 | 10 | | 47 | | 409
| | 17 | | 4 | 43 | 11 | | 53 | | 467
| | 18 | | 3 | 44 | 11 | | 60 | | 525
| | 19 | | 3 | 44 | 11 | | 67 | | 583
| | 20 | | 3 | 43 | 11 | | 73 | | 640
| | 21 | | 2 | 41 | 10 | | 79 | | 693
| | 22 | | 2 | 38 | 10 | | 85 | | 743
| | 23 | | 2 | 30 | 8 | | 89 | | 783
| | 24 | | 1 | 23 | 6 | 1 | 93 | | 814
| | 25 | | | 15 | 4 | 1 | 95 | | 834
| | 26 | | | 8 | 2 | 2 | 97 | | 846
| | 27 | | | 4 | 1 | 4 | 98 | | 855
| | 28 | | | 3 | 1 | 5 | 99 | | 864
| | 29 | | | 1 | 0 | 5 | 99 | | 870
| | 30 | | | 0 | 0 | 4 | 100 | | 874
| | 31 | | | | | 2 | 100 | | 876
|
|