Project Management Quick Reference by
Robert Perrine
Release 2.4
October 2007
Work Breakdown Structure
Work Breakdown Structure Technique
Term Description
Step 1:Decide upon the product to be delivered from this project. The key inputs into this process are the Scope Statement and the Scope Management Plan.
Step 2:Identify the major deliverables. Deliverables are both the subsystems of the product and also the process and artifacts required to run the project.
Step 3:Decompose the deliverables into work breakdown packages where the scope of each package is optimal for managing the effort. A package should be small enough to manage and large enough to appear meaningful when reporting.
Step 4:Review the WBS with the appropriate stakeholders and update as required to ensure the WBS is sufficiently detailed to define the scope while high level enough to be manageable.
ActivityThe scope of a work package is further decomposed during the Activity Definition process into activities. An activity is a grouping of related tasks.
Code of AccountsA Code of Accounts is the labeling scheme used to link the work packages together and to facilitate effective communication. The PMBOK section number scheme is an example of a Code of Accounts.
TaskA Task is the smallest subdivision of work in the project schedule. Tasks are grouped into activities and activities are grouped into work packages.
WBS ElementEvery component in the WBS is a WBS element.
Work Breakdown PackageThe WBS Package is the lowest level of the WBS. Each package should be decomposed to a manageable scope while remaining large enough to be meaningful when reporting to the stakeholders.
Work Breakdown StructureA WBS is a hierarchical representation of the elements of work required to compete the project. The WBS can be organized around the subsystems in the product, the project team organizational structure, geography or any other logical grouping. Always include the work of project management in the WBS.
sample Work Breakdown Structure diagram

Critical Path Method
Pick ONE Style and stay with it
For Me, the easiest convention is:
   Starting Point: Zero
   Addition: Early Finish = Early Start + Duration
   Increment: Early Start
= Early Finish of LATEST predecessor
 
Forward Pass
   Read the problem carefully
   Draw the diagram with your notation
   Add the values given by the Question
   Work left to right on tasks with 1 predecessor
   When tasks Join, Latest EF wins
CPM illustration
Backward Pass
   Convention going back matches forward
   Start with the End Node
   Work right to left
   Late Finish = Late Start of EARLIEST dependent
   Late Start = Late Finish - Duration
WBSID
DurationFloat
Early StartEarly Finish
Late StartLate Finish
Critical Path
   Project must have a single start and single end
   Calculate the Floats
   Float = Late Finish - Early Finish
   Critical Path is the set of Nodes with 0 Float
   Write down your answer
 
Answer the Question
   Read the problem carefully -- again
   Compare your answer to the list of answers
   Then answer the question
Relationship Example
Finish-StartBuy ticket, enter theater
Finish-FinishFinish collecting ballots, finish counting votes
Start-StartWhen pigs fly
Start-FinishInaugurate new governor, retire old governor
Fast TrackingStarting a dependent task before it's predecessor is completed.
Re-EstimatingRe-evaluating project requirements to fit the work into the allotted time.
LagDelay between the finish of one task and the start of the dependent task
LeadNegative lag
Three-point AverageExpected Duration = (Optimistic + Most Likely + Pessimistic) / 3
Weighted Average
Expected DurationE = (Optimistic + 4*Most Likely + Pessimistic) / 6
Standard DeviationSigma = (Pessimistic - Optimistic) / 6
VarianceVariance = (Sigma)^2
Crashing
   Find the Critical Path
   Only crash nodes on the Critical Path
   Work from highest Benefit/Cost order
   Crash one node at a time
   Re-Evaluate the Critical Path after every change
   Stop when the desired schedule reduction is achieved
 

Earned Value Quick Reference
Earned Value Vocabulary
ACActual Cost (to date)
BACBudget At Completion (planned budget)
CPICost Performance Index (CPI = EV / AC)
CVCost Variance (CV = EV - AC)
EACEstimate At Completion (Formulas are listed below)
ETCEstimate To Complete (ETC = EAC - AC)
EVEarned Value (EV = PV * %Complete)
PVPlanned Value: BAC for this task or CAP
SPISchedule Performance Index (SPI = EV / PV)
SVSchedule Variance (SV = EV - PV)
VACVariance At Completion (VAC = BAC - EAC)
Key Earned Value Formulas
Cost Performance IndexCPI = EV / AC
Cost VarianceCV = EV - AC
Earned Value (for a task)EV = PV * %Complete
Estimate To CompleteETC = EAC - AC
Schedule Performance IndexSPI = EV / PV
Schedule VarianceSV = EV - PV
Variance At CompletionVAC = BAC - EAC
% Schedule VarianceSV = ( EV - PV ) / PV
Earned Value diagram
Estimate At Completion Equations
EAC = AC + ETCReEstimatedWhen the project is re-estimated
EAC = AC + (BAC - EV)AtypicalWhen variances are not typical
EAC = AC + ((BAC - EV) / CPI)TypicalWhen variances should stay the same
EAC = BAC / CPITypicalProjection based upon variances to date
Estimates
Order of Magnitude-25% > +75%
Preliminary-15% > +50%
Budget-10% > +25%
Definitive-5% > +10%
Final100% Accurate
labels for the S-Curve diagram
Vocabulary that is slowly being phased out
ACWPActual Cost of Work Performed (replaced by AC)
BCWPBudgeted Cost of Work Performed (replaced by EV)
BCWSBudgeted Cost of Work Scheduled (replaced by PV)
S-Curve diagram
Derivation of EAC equations
EAC = AC + (BAC - EV) = AC + ((BAC - EV) / CPI), when CPI = 1
EAC = AC + ((BAC - EV)/CPI) = AC + BAC/CPI - EV/CPI = BAC/CPI
Hence, EAC = AC + ((BAC – EV) / CPI) is the basis for all of these special cases.

Quality Quick Reference
Term Definition
Appraisal CostsTesting, inspections and certifications to substantiate the quality of the product.
AttributeA binary, yes/no, inspection technique.
BenchmarkingCompare previous activities to the current activities as a standard for performance measurement.
ConformancePrevention plus Appraisal
Control ChartIn control when all values are within plus or minus 3 standard deviations, and 7 values never trend the same.
Design of ExperimentsA statistical study to determine which variables have the most influence.
External Failure CostsCosts after hand-off including warranty, repairs, returns and other corrective actions.
Failure CostsInternal failures are rework and scrap. External failures are service issues.
Internal Failure CostsCosts that occur within the operation such as corrective actions, scrap and rework.
Joseph M. JuranFitness for purpose. Also, grades are separate from quality.
KaizenJapanese word that means "continuous improvement". Improve the people and then the process.
Non-ConformanceFailures, both internal and external
Philip B. CrosbyZero Defects. The cost of quality is the cost of non-conformance.
Pareto DiagramAn ordered histogram. Paretos rule is that 80% of the problems will derive from 20% of the causes.
Prevention CostsCosts like planning, training and process improvements undertaken to reduce the probability of defects occurring.
Quality"Quality is 'the totality of characteristics of an entity that bear on its ability to satisfy stated or implied needs'".
Scatter DiagramPlot of the independent variable (input) against the dependent variable (output).
VariableSomething that can be measured.
W.E. Deming85% of quality is management's responsibility.

Example of a Cause and Effect diagram Standard Deviations
Sigma % of Population
168.27%
295.45%
399.73%
499.994%
599.99994%
699.9999998%
Example of a control chart Example of a scatter chart
Example of a Pareto chart Example of a Trendline chart

HR Quick Reference
Organizational Structures
Functional Weak Matrix Balanced Matrix Strong Matrix Projectized
One boss -- functional mgrTwo bossesTwo bossesTwo bossesOne boss -- project mgr
Little project focusConflicted goalsConflicted goalsConflicted goalsUncertain at project end
Focused on specializationFunction first, then projectBalance function & projectProject first then functionFocus on the project
Example of an influence curve Cost of change increases as more work is finished
 
 
 
Ability to influence drops as project nears completion
Responsibility Assignment Matrix
Activity Project Manager Project Sponsor Customer Representative User Representative
Create project charterRCCI
Create prelim scopeRICC
Create project planRICC
A - accountable
R - responsible
C - contributing
I - informed
Types of Power
Power Illustration
ReferentRespect
ExpertKnowledge
RewardGratification
LegitimateFormal
PunishmentCoercive

Lines of Communication
L = (n) * (n-1) / 2    Where n is the number of people
 
Stages of Team Formation
Stage Behaviors
FormingFormal and reserved.
StormingConfrontational while trying to define territory.
NormingComrade with consensus on decisions.
PerformingHigh levels of trust and performance.
Conflict Resolution Techniques
Technique Interpretation
Confronting#1 Solve the problem. Win-Win.
Compromising#2 Both sides loose.
SmoothingIgnore (loose-loose)
ForcingImpose a solution. Win-Lose.
WithdrawalAvoidance. Postpone resolution.

Motivational Theories
Theory Description
AchievementAchievement, Power and Affiliation.
ContingencyPeople strive for competency.
ExpectancyVictor Vroom noted that people live up to their expectations.
HerzbergHygiene Theory
   Hygiene factors prevent dissatisfaction with the work environment.
   Motivators are oriented to the satisfaction the comes with the work.
Hersey and BlanchardLife-cycle progresses from Directing to Coaching to Supporting to Delegating
MaslowHierarchy of Needs
Self Actualization = Peak performance.
Self Esteem = Respect from others and respect for self.
Social = Family, friends and community.
Safety & Security = Physical welfare.
Basic Physical = Survival necessities such as food, clothing and shelter.
McGregorTheory X managers think that people do not want to work.
Theory Y managers think people want a chance to excel at their job.
OuchiBuilding relationships of trust and commitment between the workers and management will yield increased motivation and productivity.

Leadership Styles
 Directive Behavior
LowHigh
High

Supportive
Behavior

Low
3) Supporting
Low Direction
High Support
2) Coaching
High Direction
High Support
4) Delegating
Low Direction
Low Support
1) Directing
High Direction
Low Support
Thinking Styles
 Sequential 
Concrete Fixer
Resists Change
Organizer
Team Builder
Abstract
Explorer
Entrepreneur
Intuitive
Vision
 Random 

*EMV Quick Reference * Expected Monetary Value (EMV),
also known as a Decision Tree
Step 1: List the alternatives Step 2: Assign Probabilities Step 3: Draw the Tree
EMV diagram 1 EMV diagram 2 EMV diagram 3
Step 4: Assign probable benefits and costs Step 1: List the alternatives
Step 2: Assign probabilities
Step 3: Draw the tree
Step 4: Assign probable benefits and costs
Step 5: Calculate the expected value
  Net Revenue = (Benefit – Cost)
  Expected Value = (Net Revenue) * (Probability)
  Expected Value at a junction is the sum of the branches
  Work every branch and junction from right to left
Step 6: Solve
  Either for the whole
  Or to identify the best branches
EMV diagram 4
Step 5: Calculate the expected value Step 6: Solve
EMV diagram 5
700
360
1060

Risk Strategies
NameDescription
Risk AcceptanceRisk Acceptance means choosing to take no other action. Most projects accept the risk that a meteor might extinguish life on earth and take no action to avoid or mitigate that risk.
Risk AvoidanceRisk Avoidance means taking a specific action that prevents this risk from materializing. For example, many companies have a policy against flying an entire team on the same airplane to avoid loosing the entire team in one accident.
Risk MitigationRisk Mitigation minimizes the impact. For example, passwords mitigate, but do not avoid the risk from a hacker.
Risk TransferenceRisk Transference assigns the risk to someone else. Insurance is a common form of transference.
Residual RisksRisks that are not accounted for specifically. Generally these risks are covered by the contingency fund.
Secondary RisksSide-effects from following a risk mitigation strategy.

Project Terminations
NameDescription
AdditionAddition into normal operations through evolution.
StarvationStarved of resources or budget.
IntegrationIntegrated into other projects or operations at the expense of this project.
ExtinctionExtinct because it finished; the project concluded.

Finance Quick Reference
Term Definition
Payback PeriodOccurs when: Sum(Total Project Costs) = Sum(Accumulated benefits)
Future ValueFV = PV * (1 + i)^n
Present ValuePV = FV / (1 + i)^n
Net Present ValueNPV = PV(Benefits) - PV(Costs)
Internal Rate of ReturnInterest Rate when NPV = 0
Direct CostsCosts directly chargeable to the project. Contract labor is often a direct cost.
Fixed CostsCosts that are charged at a specific price regardless of hours used or units produced, such as rent.
Indirect CostsOverhead costs that are charged to the project, such as building insurance.
Opportunity CostsThe lost benefit that comes about from choosing one project or alternative over another.
Sunk CostsExpenses already incurred. Do not count Sunk Costs when comparing future alternatives.
Variable CostsCosts that increase per hour or per unit.
Fixed Price ContractsLump Sum, Fixed Price plus Incentive, Unit Price. Seller has the most risk. Useful if the project has a high value or if it is expected to take a long time to complete.
Cost Reimbursable ContractsCost Plus Fixed Fee, Cost Plus Incentive Fee. Buyer has the most risk. Use when there is a lot of uncertainty or a large payment required early in the project.
Time & Material ContractsSomewhere between Fixed Price and Cost Reimbursable.
Top-Down or Analogous EstimatingInitial estimates are typically made from a top-down perspective based upon similarities to historical projects. For example, if the scope of a new project seems to imply the need for three new screens, and a previous project that required two new screens took 4 days, the initial estimate for the new project would be 6 days. Such estimates are sufficient for the project charter. Additionally, many smaller projects do not justify a more elaborate estimate.
Parametric EstimatingMultiply the number of things by some unit. For software this is the COCOMO method. It is more common in construction with $/sq ft or hours/cubic yard.
Bottom-Up EstimatingLarger projects, however, cannot easily be estimated as a whole. For larger projects IT has traditionally identified the detailed tasks and then estimated each individual task. This is a bottom-up approach. Both approaches utilizes the expert opinion of the person responsible for the work. Both approaches rely upon historical records of previous projects. On small projects, one person can usually provide the estimate for the entire project. On large projects, the task durations are typically estimated by the various managers responsible for each task area. Those estimates are then combined with the work breakdown structure so that resource allocations and resource leveling can be considered when deriving an estimate of the total project duration.

Net Present Value Example
Term Year 1 Year 2 Year 3 Year 4 Year 5 Project Total
Development35,000.0045,000.005,000.00- - 85,000.00
Licensing10,000.0030,000.0010,000.0010,000.0010,000.0070,000.00
Maintenance- 5,000.005,000.0010,000.005,000.0025,000.00
Total Annual Cost45,000.0080,000.0020,000.0020,000.0015,000.00180,000.00
Revenues4,000.0025,000.0050,000.0070,000.0080,000.00229,000.00
Net Annual Revenue(41,000.00)(55,000.00)30,000.0050,000.0065,000.0049,000.00
   10.0% Present Value(37,272.73)(45,454.55)22,539.4434,150.6740,359.8914,322.73
   16.9% IRR (by trial and error)(35,071.36)(40,243.92)18,777.0626,769.8029,768.520.10
Cumulative Costs45,000.00125,000.00145,000.00165,000.00180,000.00 
Cumulative Revenue4,000.0029,000.0079,000.00149,000.00229,000.00 
Cumulative Net(41,000.00)(96,000.00)(66,000.00)(16,000.00)49,000.00 

Chart illustrating break even calculations

 

Legend for the following Charts
AbbrevUsage
Embedded
CCreate
IInput
I/UInput and Update
TTool or Technique
UUpdate
Color Codes
Integration   Quality   Procurement
Scope   Human Resources   External or Unknown
Time   Communications   Multiple sources
Cost   Risk  

 

Relationship of Domains, Process Groups and Knowledge Areas


Knowledge Areas Domains
Process Groups Professional
Responsibility
Initiating Planning Executing Monitoring and Controlling Closing
Integration Develop Project Charter Develop Project Management Plan Direct and Manage Project Execution Monitor and Control Project Work Close Project yes
Develop Preliminary Project Scope Statement Integrated Change Control
Scope Scope Planning Scope Verification yes
Scope Definition Scope Control
Create WBS
Time Activity Definition Schedule Control yes
Activity Sequencing
Activity Resource Estimating
Activity Duration Estimating
Schedule Development
Cost Cost Estimating Cost Control yes
Cost Budgeting
Quality Quality Planning Perform Quality Assurance Perform Quality Control yes
Human Resources Human Resource Planning Acquire Project Team Manage Project Team yes
Develop Project Team
Communications Communications Planning Information Distribution Performance Reporting yes
Manage Stakeholders
Risk Risk Management Planning Risk Monitoring and Control yes
Risk Identification
Qualitative Risk Analysis
Quantitative Risk Analysis
Risk Response Planning
Procurement Plan Purchases and Acquisitions Request Seller Responses Contract Administration Contract Closure yes
Plan Contracting Select Sellers

Project
Management
Artifacts
Process Name
Artifact Name
Initiation   Planning   Executing   Monitoring and Controlling   Closure
Develop Project Charter Develop Preliminary Project Scope Statement   Develop Project Management Plan Scope Planning Scope Definition Create WBS Activity Definition Activity Sequencing Activity Resource Estimating Activity Duration Estimating Schedule Development Cost Estimating Cost Budgeting Quality Planning Human Resource Planning Communications Planning Risk Management Planning Risk Identification Qualitative Risk Analysis Quantitative Risk Analysis Risk Response Planning Plan Purchases and Acquisitions Plan Contracting   Direct and Manage Project Execution Perform Quality Assurance Acquire Project Team Develop Project Team Information Distribution Request Seller Responses Select Sellers   Monitor and Control Project Work Integrated Change Control Scope Verification Scope Control Schedule Control Cost Control Perform Quality Control Manage Project Team Performance Reporting Manage Stakeholders Risk Monitoring and Control Contract Administration   Close Project Contract Closure
Accepted deliverables                                                                       C                        
Activity attributes               C I/U I/U I/U I/U                                                   U                    
Activity cost estimates                   I   C I                 I I                             U                  
Activity cost estimates supporting detail                         C I                                                                    
Activity duration estimates                     C I                                                                        
Activity list               C I/U I I I                                                   U                    
Activity res reqs / Resource requirements                 C I I/U                     I I                                                
Administrative closure procedure                                                   I                                         C  
Approved change requests           I I   I                                 I I               C I   I I I   I C I I      
Approved corrective actions                                                   I                 C               C          
Approved defect repair                                                   I                 C                          
Approved preventative actions                                                   I                 C                          
Assumptions       C                         I                                                              
Closed contracts                                                                                               C
Communications management plan                               C                         I                         I          
Constraints       C                         I                                                              
Contract (external) I                         I                                                                    
Contract (solicitation)                                                               C                         I      
Contract closure procedure                                                                                             C I
Contract documentation                                                                                         C   I I
Contract management plan                                                             C                         I/U     I
Contract statement of work                                             C I/U                                                
Cost baseline                         C                 I I                             I/U                  
Cost management plan       C                 U I/U             I                                                      
Deliverables                                                   C                 I/U I       I   I         I  
Enterprise environmental factors I I   I I     I   I I   I   I   I I I       I         I                                     I  
Evaluation criteria                                               C               I                                
Final product, service or result                                                                                             C  
Forecast completion                                                                             C     I            
Forecasts                                                                   C               C            
Implemented change requests                                                   C I                                          
Implemented corrective actions                                                   C I                                          
Implemented defect repairs                                                   C I                                          
Implemented preventative actions                                                   C I                                          
Make-or-buy decisions                                             C I                                                
Milestone list             C I                                                                              
Organizational process assets I I   I I I I I   I I I I   I   I I I I I   I       U I   U I I         U U U I/U I/U U I/U U U   I/U U
Performance measurement baseline       C                                                                           I            
Performance measurements                                                                           C C     I            
Performance reports                                                                       I   I I   I C   I I      
Preliminary project scope statement   C   I I I         I                                                                          
Process improvement plan                           C                       I                                          
Procurement document package                                                             C I                                
Procurement documents                                               C             I                                  
Procurement management plan                                           C I             I I/U                         U      
Project charter C I     I I                                                                                    
Project funding requirements                           C                                                 I                  
Project management plan       C I     I   I I I/U I/U   I/U   I I I   I U I I   I U             I I/U   U U I/U U I/U I U U U   I I
Project management processes       I                                                                                        
Project organizational charts                               C                       I                         I              
Project schedule                     C   I               I I I                                                
Project schedule network diagrams                 C     I                                                                        
Project scope management plan       C I/U I/U                                                         I I                      
Project scope statement           C I/U I I     I I I I   I I I I I   I                       U I I/U                      
Project staff assignments                                                       C I                       I              
Project statement of work I I                                                                                            
Proposals                                                             C I                                
Qualified sellers list                                                             C I                                
Quality baseline                           C                                                 U                
Quality checklists                             C                                                 I                
Quality control measurements                                                     I                         C   I            
Quality management plan                           C                       I                         I                
Quality metrics                             C                       I                         I                
Recommended corrective actions                                                     C             C I C C C C C C C   C C      
Recommended defect repair                                                                   C I         C                
Recommended preventative actions                                                                   C I         C C     C        
Rejected change requests                                                                   I C                          
Requested changes           C C C C C   C C C                 C     C C     C   C   C I C C C C C   C   C C      
Resolved issues                                                                                     C          
Resource availability (org. asset)                   I                                                                            
Resource availability                                                       C I     U                                
Resource breakdown structure                   C                                                                            
Resource calendar / Project calendar                   U I I/U   I                                                                    
Risk management plan                                 C I I I I                                           I        
Risk register                   I I I           C I/U I/U I/U I I               I                       U        
Risk-related contractual agreements                                         C I I               I                                
Roles and responsibilities                               C                       I                         I              
Schedule baseline                     C                                                   I/U                    
Schedule management plan       C               U I               I                                 I                    
Schedule model data                       C                                                   U                    
Scope baseline             C                                                           U                      
Selected sellers                                                               C                         I      
Staffing management plan                       I     C                       I/U I                       I              
Team performance assessment                                                         C                       I              
Validated defect repair                                                   I                 C         C                
Validated deliverables                                                                               C                
WBS dictionary             C I         I I                 I                         I I/U                      
Work breakdown structure             C I         I I                 I                           I/U                      
Work performance information                                                   C I             I I I     I I I I   I I   I  

 
 
 
 
Project
Management
Tools and
Techniques
Process Name
Name of the Tool or Technique
Initiation   Planning   Executing   Monitoring and Controlling   Closure
Develop Project Charter Develop Preliminary Project Scope Statement   Develop Project Management Plan Scope Planning Scope Definition Create WBS Activity Definition Activity Sequencing Activity Resource Estimating Activity Duration Estimating Schedule Development Cost Estimating Cost Budgeting Quality Planning Human Resource Planning Communications Planning Risk Management Planning Risk Identification Qualitative Risk Analysis Quantitative Risk Analysis Risk Response Planning Plan Purchases and Acquisitions Plan Contracting   Direct and Manage Project Execution Perform Quality Assurance Acquire Project Team Develop Project Team Information Distribution Request Seller Responses Select Sellers   Monitor and Control Project Work Integrated Change Control Scope Verification Scope Control Schedule Control Cost Control Perform Quality Control Manage Project Team Performance Reporting Manage Stakeholders Risk Monitoring and Control Contract Administration   Close Project Contract Closure
Acquisition                                                       T                                        
Additional quality planning tools                             T                                                                  
Advertising                                                             T                                  
Alternatives analysis                   T                                                                            
Alternatives identification           T                                                                                    
Analogous estimating                     T   T                                                                      
Applying calendars                       T                                                                        
Applying leads and lags                 T     T                                                                        
Arrow Diagramming Method (ADM)                 T                                                                              
Assumptions analysis                                     T                                                          
Benchmarking                             T                                                                  
Bidder conferences                                                             T                                  
Bottom-up estimating                   T     T                                                                      
Buyer-conducted performance review                                                                                         T      
Cause and effect diagrams                                                                               T                
Change control system                                                                         T                      
Checklist analysis                                     T                                                          
Claims administration                                                                                         T      
Co-location                                                         T                                      
Communications methods                                                                                   T            
Communications requirements analysis                                 T                                                              
Communications skills                                                           T                                    
Communications technology                                 T                                                              
Contingent response strategy                                           T                                                    
Control charts                                                                               T                
Configuration management system                                                                         T                      
Conflict management                                                                                 T              
Contract change control system                                                                                         T      
Contract negotiation                                                               T                                
Contract types                                             T                                                  
Cost aggregation                           T                                                                    
Cost-benefit analysis                             T                                                                  
Cost change control system                                                                             T                  
Cost of quality                         T   T                                                                  
Cost reporting systems                                                                                   T            
Critical chain method                       T                                                                        
Critical path method                       T                                                                        
Data gathering and representation techniques                                         T                                                      
Decomposition             T T                                                                                
Defect repair review                                                                               T                
Dependency determination                 T                                                                              
Design of experiments                             T                                                                  
Determine resource cost rates                         T                                                                      
Develop qualified sellers list                                                             T                                  
Diagramming techniques                                     T                                                          
Documentation reviews                                     T                                                          
Earned value management                                                                   T                            
Expert judgment T T   T T T T T   T T                       T T               T   T T                       T  
Flowcharting                                                                               T                
Forecasting                                                                             T                  
Funding limit reconciliation                           T                                                                    
General management skills                                                         T                                      
Ground rules                                                         T                                      
Histogram                                                                               T                
Independent estimates                                                               T                                
Information gathering and retrieval system                                                           T                                    
Information gathering techniques                                     T                                                          
Information distribution methods                                                           T                                    
Information presentation tools                                                                                   T            
Information technology                                                                                         T      
Inspection / Inspections and audits                                                                       T       T         T      
Issue log                                                                                 T T            
Lessons learned process                                                           T                                    
Make-or-buy analysis                                             T                                                  
Negotiation                                                       T                                        
Networking                               T                                                                
Observation and conversation                                                                                 T              
Organization charts and position descriptions                               T                                                                
Organizational theory                               T                                                                
Parametric estimating                     T   T T                                                                    
Pareto chart                                                                               T                
Payment system                                                                                         T      
Planning component               T                                                                                
Planning meetings and analysis                                   T                                                            
Pre-assignment                                                       T                                        
Precedence Diagramming Method (PDM)                 T                                                                              
Performance information gathering and compilation                                                                                   T            
Performance measurement                                                                           T                    
Performance measurement analysis                                                                             T                  
Performance reporting                                                                                         T      
Probability and impact matrix                                       T                                                        
Process analysis                                                     T                                          
Procurement audits                                                                                               T
Product analysis           T                                                                                    
Progress reporting                                                                           T                    
Project management information system T T   T                                           T               T T                       T  
Project management methodology T T   T                                           T               T T                       T  
Project management software                   T     T                                                 T T                  
Project performance appraisals                                                                                 T              
Project performance reviews                                                                             T                  
Project selection methods T                                                                                              
Proposal evaluation techniques                                                               T                                
Published estimating data                   T                                                                            
Quality audits                                                     T                                          
Quality control tools and techniques                                                     T                                          
Quality planning tools and techniques                                                     T                                          
Quantitative risk analysis and modeling techniques                                         T                                                      
Recognition and rewards                                                         T                                      
Records management system                                                                                         T     T
Replanning                                                                         T                      
Reserve analysis                     T   T T                                                           T        
Resource leveling                       T                                                                        
Risk audits                                                                                       T        
Risk categorization                                       T                                                        
Risk data quality assessments                                       T                                                        
Risk probability and impact assessment                                       T                                                        
Risk reassessment                                                                                       T        
Risk urgency assessment                                       T                                                        
Rolling wave planning               T                                                                                
Run chart                                                                               T                
Scatter diagram                                                                               T                
Schedule change control system                                                                           T                    
Schedule comparison bar charts                                                                           T                    
Schedule compression                       T                                                                        
Schedule model                       T                                                                        
Schedule network analysis                       T                                                                        
Schedule network templates                 T                                                                              
Screening systems                                                               T                                
Seller rating systems                                                               T                                
Stakeholder analysis           T                                                                                    
Standard forms                                               T                                                
Statistical sampling                                                                               T                
Status review meetings / Status meetings                                                                                   T   T        
Strategies for both threats and opportunities                                           T                                                    
Strategies for negative risk or threats                                           T                                                    
Strategies for positive risk or threats                                           T                                                    
Team-building activities                                                         T                                      
Technical performance measurement                                                                                       T        
Templates               T                                                                                
Templates, forms, standards         T                                                                                      
Three-point estimates                     T                                                                          
Time reporting systems                                                                                   T            
Training                                                         T                                      
Variance analysis                                                                         T T                    
Variance management                                                                             T                  
Variance and trend analysis                                                                                       T        
Vendor bid analysis                         T                                                                      
Virtual teams                                                       T                                        
Weighting system                                                               T                                
What-if scenario analysis                       T                                                                        
Work breakdown structure templates             T                                                                                  

Chart to illustrate the Initiation and Planning process flows

 

Chart to illustrate the Executing, Monitoring and Controlling and the Closing process flows

 
This final chart includes a word of caution. This is a handy reference to help you understand that the ouputs from one process become the inputs to other processes. Of all the information that I have included in this Quick Reference guide, this final chart is the most subjective. Use it with caution. I hope it helps you understand the concept.

 
Key Input Process Key Output
Initiating
Contract (external) Develop Project Charter Project charter
Project charter Develop Preliminary Project Scope Statement Preliminary project scope statement
Planning
Project management processes Develop Project Management Plan Project management plan
Project management plan Scope Planning Project scope management plan
Project scope management plan Scope Definition Project scope statement
Project scope statement Create WBS Work breakdown structure
WBS & WBS dictionary Activity Definition Activity list
Activity list & attributes Activity Sequencing Project schedule network diagrams
Resource availability Activity Resource Estimating Activity resource requirements
Activity resource requirements Activity Duration Estimating Activity duration estimates
Activity duration estimates Schedule Development Project schedule
WBS & WBS dictionary Cost Estimating Activity cost estimates
Activity cost estimates Cost Budgeting Cost baseline
Project scope statement Quality Planning Quality management plan
Activity resource requirements Human Resource Planning Staffing management plan
Constraints & Assumptions Communications Planning Communications management plan
Project scope statement Risk Management Planning Risk management plan
Risk management plan Risk Identification Risk register
Risk register Qualitative Risk Analysis Risk register (updates)
Risk register Quantitative Risk Analysis Risk register (updates)
Risk register Risk Response Planning Risk register (updates)
WBS & WBS dictionary Plan Purchases and Acquisitions Contract statement of work
Contract statement of work Plan Contracting Procurement documents
Executing
Approved change requests, etc Direct and Manage Project Execution Deliverables
Quality metrics Perform Quality Assurance Recommended corrective actions
Project organizational charts Acquire Project Team Project staff assignments
Resource availability Develop Project Team Team performance assessment
Communications management plan Information Distribution Organizational process assets
Procurement documents Request Seller Responses Proposals
Proposals Select Sellers Contract (solicitation)
Monitoring & Controlling
Work performance information Monitor and Control Project Work Recommended corrective actions, etc
Recommended corrective actions, etc Integrated Change Control Approved change requests, etc
Deliverables Scope Verification Accepted deliverables
Performance reports Scope Control Recommended corrective actions, etc
Performance reports Schedule Control Recommended corrective actions, etc
Performance reports Cost Control Recommended corrective actions, etc
Quality metrics Perform Quality Control Recommended corrective actions, etc
Team performance assessment Manage Project Team Recommended corrective actions, etc
Performance measurements Performance Reporting Performance reports
Communications management plan Manage Stakeholders Resolved issues
Risk register Risk Monitoring and Control Recommended corrective actions, etc
Contract (solicitation) Contract Administration Recommended corrective actions, etc
Closing
Deliverables Close Project Final product, service or result
Contract documentation Contract Closure Closed contracts

 
References

A Guide to the Project Management Body of Knowledge (PMBOK Guide); Project Management Institute; 2004; ISBN 193069945-X

Achieve PMP® Exam Success; Margaret Chu, PMP, Diane Altwies, PMP, and Edward Walker, PMP; J. Ross Publishing; 2005; ISBN 1-932159-37-1; http://www.jrosspub.com/Engine/Shopping/catalog.asp?store=12&category=189&itempage=1&item=13164&itemonly=1 http://www.outercoreinc.com

Hot Topics PMP Exam Flashcards, 5th edition; Rita Mulcahy, PMP; RMC Publishing; http://www.rmcproject.com/

Information Technology Project Management; Kathy Schwalbe; Course Technology Inc; 0-619-03528-5

PMI Compendium of Project Management Practices; Project Management Institute; 2003; 1-930699-02-6

PMI on-line PMP Certification application form; https://certificationapp.pmi.org/

PMP Project Management Professional Study Guide, 3rd edition; Kim Heldman, PMP; Sybex; 0-7821-3601-X; http://www.kimheldman.com/

PMP Role Delineation Study; Project Management Institute; 2000; 1-880410-29-X

Practice Standard for Work Breakdown Structures; Project Management Institute; 2001; 1-880410-81-8

Project Management Institute; http://www.pmi.org

Project Management Institute, Orange County Chapter; http://www.pmi-oc.org

Project Management International, Continuing Certification Requirements Handbook; http://www.pmi.org/info/PDC_CCRHandbook.pdf

Project Management International, On-Line PDU Entry Form; http://www.occe.ou.edu/aia/pmi/PDUlogin.php3

Project Management International, Project Management Professional Certification Handbook; http://www.pmi.org/info/PDC_PMPHandbook.pdf

Project Management International, Project Management Professional Code of Professional Conduct; http://www.pmi.org/prod/groups/public/documents/info/PDC_PMPCodeOfConduct.pdf

Project Management, A Systems Approach to Planning, Scheduling and Controlling; Harold Kerzner, Ph.D.; John Wiley; 0-471-22577-0
 

Copyright Robert E. Perrine, PMP, ITIL-SM, CISA, MBB
About Robert E. Perrine, PMP, ITIL-SM, CISA, MBB